Our Construction

HOME     Our Construction     Civil Engineering     Furukawa Viaduct

Furukawa Viaduct

Category
Bridges
Bridge Type, Construction Method, etc
Precast segmental bridges
Construction site
Mie Prefecture
Completion date
1999

Name Furukawa Viaduct
Ordered by NEXCO Central Nippon No. 2 Meishin Expressway
Awards Japan Society of Civil Engineers, Tanaka Award; Japan Prestressed Concrete Institute Award for Outstanding Structures; Japan Prestressed Concrete Engineering Association Award
Construction site Mie Prefecture
Completed 1999
Bridge length 1,475 m
Effective width 15.5 m
Construction outline (9+9+13+10) span continuous girder bridge
The main girders have a composite structure comprised of factory-made U-shaped (open cross-section) segments and PC slabs, and it is the world’s first structure to be erected via a span-by-span construction method utilizing open cross-section precast segments.